|

|
STATE OF MICHIGAN
HOUSE OF REPRESENTATIVES OFFICE BUILDING
Lansing, Michigan
|
I. Project Description
The new State of Michigan House of Representatives
fourteen-story complex, built at a cost
of $40,000,000, brings State Legislators,
their staff, and the House support departments
into one building centrally located in downtown
Lansing across the street from the historic
State Capitol. The location at the corner
of Capitol Avenue and Ottawa Street presented
a winning opportunity for relocating the
710 persons involved with the House of Representatives,
who previously occupied several buildings
dispersed around the city, into this class
environment with adjacency to the Capitol.
|

|
|
The House building comprised three individual
structures framed with a total of 2,540
tons of structural steel. The project involved
the redevelopment of two sites on either
side of Ottawa Street and the connection
of those two sites. The result presents
two office towers with a third bridge building
serving as the connection. This three-part
frontage afforded the opportunity to develop
identical office suites for all 110 Representatives,
each facing the Capitol Building. Feature
windows, located at each suite, provide
views of the entire State of Michigan government
complex. Also featured are hearing rooms,
a committee center, conference and reception
services, a lobby restaurant, and underground
parking.
The three major building components involved
vertical expansion of the City of Lansing
Board of Water and Light Building from a
nine and five story to a fourteen-story
tower, demolition of an existing eight-story
building and replacement with a new eleven-story
tower along with construction of a seven-story
bridge building suspended 65 feet over Ottawa
Street.
II. Design and Construction Challenges
- Schedule
At the onset of the project, the design
and construction team was faced with
a very aggressive schedule of twenty
(20) months from the inception through
completion.
- Board of Water and Light Building
Vertical Expansion
Technically, most challenging was
the existing Board of Water and Light
Building expansion. A portion of the
building had nine (9) floors, while
the remaining had five (5). The building
program required addition of five
(5) and nine (9) levels respectively,
on top of the existing structural
framework. It required considerable
structural upgrading to receive additional
floor loads and to resist lateral
wind and seismic loads. New columns
were threaded through the existing
floors to bear on mini-pile foundations
drilled through the basement floor.
During the construction, portions
of the building were still occupied
by the Board of Water and Light employees.
This required new columns to be strategically
located and installed without disturbing
the tenant spaces. Columns with 2-inch
thick flanges were full penetration
welded at the lower shaft splice points.
Lateral Load Resistance
The existing structure was designed
with AISC type 2 connections to resist
lateral loads. New braced bays were
added to resist current code required
lateral loads. The bracing connections
needed to be custom fit to the existing
beam connections. At many locations,
due to space being occupied, permanent
bracing could not be installed. Desai/Nasr
designed temporary bracing within
the existing structure to resist lateral
loads, so that precast panel erection
could continue uninterrupted to maintain
aggressive project schedule.
Reinforcement of Existing Columns
and Beams
Many existing beams and columns were
reinforced to resist additional loading.
In the extreme cases, beams carrying
concentrated loads from new columns
were reinforced with a heavy WT- section
welded to the bottom flange in conjunction
with reinforcement of existing connections.
In many cases were columns needed
reinforcement in two or more adjacent
levels, the engineers at Desai/Nasr
designed column reinforcement to be
continuous through penetrations in
existing concrete floor. A typical
configuration consisted of four (4)
plates each welded to one edge of
column flanges; this allowed reinforcing
plates to run through the floor without
interference with beam-to-column connections.
This configuration also has the added
advantage of reversing the residual
stresses in the existing column thus
favorably unleashing its reserve capacity.
Several other reinforcement configurations
were designed to accommodate various
situations. Heavy WT-sections (e.g.
WT9x71.5) were used to reinforce exterior
columns carrying loads from nine (9)
additional stories. In all cases of
column reinforcement, the effect of
shift in column centriod on load eccentricity
was taken into consideration.
Interior Column Removal
Besides requiring localized reinforcement
of beams, columns and connections,
it was discovered that in the newly
planned hearing room on the 5th floor
an existing column interfered with
the Chairman's desk. This required
removal of a column between the 5th
and 6th floors. In order to move the
interfering column, the adjacent existing
columns were reinforced. New W36 X
280 transfer beams were threaded through
one of the window openings, raised
to their final supporting positions,
and attached to the existing column.
After all the connections were made,
the column was cut and removed. The
beams were designed to deflect due
to dead load no more than 1/4" to
avoid cracking of four (4) supported
floors above.
- North Capitol Building
In the mean time, Desai/Nasr and
Douglas Steel determined that it would
be more cost effective to demolish
the eight-story structure across the
Ottawa street, to accommodate the
11 floors needed to provide the required
square footage. Desai/Nasr worked
closely with the Project Architect,
Hobbs & Black, to determine the column
location to avoid interference with
the existing structure building. All
the exterior columns had to be located
inbound by 8' from the exterior, and
resulted in cantilevering all 11 floors.
Desai/Nasr and NuCon precast panel
contractor designed panel connections
to the structure to accommodate differential
floor deflection at the cantilevered
ends. Small building footprint (70'
X 70') compared to the building height,
(154') presented a challenge to resist
lateral loads. Rigid frames in combination
with wide flange K-braces were designed
with high-strength bolted connections
to speed the erection of the frame.
- Ottawa Street Bridge Building
Desai/Nasr faced additional challenges
in interfacing the two towers located
across the four-lane Ottawa Street and
designed three 30' deep Vierendeel trusses
to support seven floors totaling 37000
square feet space over the street. The
trusses were integrated into the three
lower floors and were primarily framed
with W14X398 sections. All the trusses
were fabricated in Atree@ shapes with
full penetration welds and shipped from
South Carolina and field connected with
over 7000 - 1 1/8" diameter A490 bolts.
Five-story shoring towers were erected
on mats beneath the tower to temporarily
support trusses until assembly and splicing
were complete. Desai/Nasr analyzed and
designed the trusses to account for
incremental construction loads to ensure
level floor elevations in final use.
The trusses were supported on 65 foot
high composite columns consisting of
W14 x 398 steel sections and 6000 psi
concrete bearing on caisson foundations.
Due to below grade interference, the
columns could not be located to align
with any of the nodes of the Vierendeel
truss. A special V shape knee bracing
assembly was designed at the top of
the columns to transfer the forces from
the Vierendeel nodes to these columns.
The Mackinac Room located on the fifth
floor of the bridge structure with a
stunning seven-story stained glass window
provides 5000 sq.ft assembly space and
features views of the State Governmental
complex on the west and the Grand River
and Lansing Convention Center on the
east.
Due to the fast pace of construction
on this complex structure, fabrication
was being performed as the design was
developing. Mill orders were placed
based on initial design, with final
design and detailing being completed
as the raw material was arriving for
fabrication. At times fabrications was
performed prior to shop drawing approval
with some modifications being made in
the field. The required modifications
could not have been achieved had the
existing building been framed using
reinforced concrete.
- Engineering Software:
STAAD.Pro was used to verify
the design of the Vierendeel trusses
and to calculate the axial loads in
the Vierendeel beams which could not
be obtained from other programs as
most programs assign the axial force
to the rigid diaphragm. Other Engineering
software such as Enercalc and Ecom
has been used for foundation design
and for analysis and design of individual
steel and concrete members. In-house
computer programs were developed and
used to design and check column and
beam reinforcement.
- Site Safety, Space Restrictions
and Accessibility Problems:
- Initially, steel erection had to
be scheduled during nights and weekends
to assure the safety of the building
occupants working just below the new
levels of steel. Erection had to flow
closely behind the surgical demolition
and abatement of the occupied building.
- In an attempt to manage the limited
site space and maximize the efficiency
of the hoisting operation, Granger
Group took control of the crane, a
200 ton Manitowoc M888. During periods
of the project, steel was being erected
by day and precast by night using
the same crane.
- Erection of the North Capitol Building
was delicate work as the new steel
frame came within inches of a neighboring
historic landmark building.
- Satisfying Owner's Program
Mr. Bill Frank of Granger Group said:
Desai/Nasr met and exceeded Owner/Client's
needs by utilizing reserve capacity
of the Board of Water and Light buildings=
columns and foundations, strategically
locating and designing new column locations
so that the columns could be installed
while the building was still occupied.
Further, Desai/Nasr solved the problem
of integrating the two office towers
located on each side of Ottawa Street,
by designing the 30' deep Vierendeel
Trusses, which allowed the owner to
provide seven floors of the office/assembly
function spaces over a roadway. The
integrated 300,000 sq.ft structure provided
a simple and seamless flow of traffic
for the staff, and easy access for the
visitors.
- Economic Impact
The House of Representatives building
consolidated all house offices and
functions at one location. The building
also provided a permanent office for
each district and saved the Michigan
tax payers the cost of moving expenses
estimated to be several thousand dollars
after each election year.
|
|
|
|
|